The Trail Blazers are “very far apart” in their negotiations with the city of Portland to provide public funding for renovations to the Moda Center, a team source tells Jason Quick of The Athletic.

City officials sent the Blazers a term sheet on Friday outlining a 20-year lease agreement that includes $600MM in public funds to upgrade the arena. Quick notes that Portland is asking the team to pay $3MM per year for a property tax offset, which would increase over time. The proposal also requires the team to hire union workers and set caps on cost overruns.

“The term sheet is a non-starter,’’ Quick’s source said. “I don’t know why they sent it to us, because they know very little of the stuff we would agree to. They are playing politics at this point.”

The team’s board of directors will meet later today to discuss the offer and prepare a response. The city has scheduled a vote on funding for August 12, and Quick notes that a deal must be reached by the end of the year for the offer to include state funds.

There are fears that failure to reach an agreement could result in the Trail Blazers leaving Portland when their lease at the arena expires in 2030. There’s “unspoken tension” that new owner Tom Dundon would consider relocating the team, but Quick hears from two high-ranking sources in the organization that Dundon has never mentioned that as a possibility.

“No one with the Blazers has ever said we want to move,’’ one of the sources said. “We don’t want that. We want to stay in Portland.’’

Quick points out that the relationship between the Blazers and city officials has become strained, with both sides accusing each other of operating in bad faith. Some council members believe the team hasn’t been open about how it plans to spend the money from the city.

“I think the Blazers have been behaving poorly,’’ councilor Mitch Green said. “They thought because they passed the state legislature (for $365MM in funding) that the deal was done. But we have a set of councilors who are asking tough questions. And this is Portland, Oregon, where people want more public transparency than there has been.’’

The Blazers contend they haven’t shared their renovation plans because they’re currently just “ideas or concepts,” and they’re upset that councilor Steve Novick threatened to sue the team last month for failing to properly maintain the Moda Center.

“We don’t even want to respond to the term sheet until they remove that gun to our head,’’ a team source told The Athletic.

Another Trail Blazers source told Quick that they’re reluctant to go into detail with council about their renovation ideas until they’re sure that the information won’t become part of a lawsuit.

According to Quick, the Blazers’ plans include a new atrium entrance on the north side of the arena that would provide for easier traffic flow. They also want to place kitchens on all three levels to provide more concession options, eliminate some seating and create a bar area, and update the club-level seats.

Quick notes that team officials thought a deal with the city was secure after the state made a $365MM commitment in March to renovate the arena. However, that arrangement is contingent on the city of Portland agreeing to provide $120MM, plus another $88MM from Multnomah County. The Blazers contend that a “handshake agreement” with all three entities took place and they don’t understand why things have changed.

Quick also hears that team officials have been examining recent arena deals in Oklahoma City and Utah as they explore their options, which may include trying to get a new facility in Portland.

“The city’s delay has given us time to study what a market deal is,’’ Quick’s source said. “And let’s just say the $600MM deal that was supposed to be done six months ago was a way-below-market deal.’’

View Comments (42)